Updates & News
June 25, 2004 - Post Tension for car park is completed.
June 26, 2004 - Concrete being poured for the car park area.
July 7, 2004 - Second floor concrete being poured over the post tention.
July 7, 2004 - Second floor pour completed
July 23, 2004 - 3rd floor concrete completed
July 31, 2004 - 4th floor concrete being poured
July 31, 2004 - Lobby internal walls going up as the concrete is poured for the 4th floor.
August 1, 2004 - Structure through 4th floor complete
August 11, 2004 - 5th floor structure completed
August 19, 2004 - 6th floor post tention cables being set
August 20, 2004 - 6th floor structure completed
Sept 3, 2004 - Photo of the construction showing the recently completed 7th floor. We plan to pour the concrete for the roof on the 15th completing the structural phase of the project.