Updates & News
September 7, 2004 - Work continues on internal walls.
September 7, 2004 - Rooms begin to take shape.
Sept 23, 2004 - Rooftop completed and formwork being removed. Internal wall construction continuing on all floors.

November 29, 2004 - Roof-top water storage tank and wading pool concrete being poured.

Also in veiw - work progressing on the facade entrance of the building.

Structural architecture nearly complete on floors 1 through 3; tiles being laid in some areas and woodwork in progress.

pattaya condo

January 5, 2005 - Finishing plaster work completed for the front entrance facade.

condo pattaya
January 17, 2005 - Marble and Granite floor being layed in the lobby reception area.
condos pattaya thailand
January 17, 2005 - Marble and Granite floor in lobby reception area.
condos pattaya