| September 10, 2003 - Piling begins |
![]() |
|
| September / October, 2003 - 3 crews at work piling to bed-rock at a depth of 17 meters. In total, 84 piles are set. |
![]() |
|
| Rebar is hoisted and inserted into the completed pile holes in preparation for concrete. |
![]() |
|
| November 10, 2003 - Forms are laid for the pile caps. The general configuration is 5 piles joined by 1 pile cap platform. |
![]() |
|
| November 25, 2003 - A number of completed pile caps in the restaurant kitchen area. |
![]() |
|
| Dec 4, 2003 - Pouring the floor for the main water storage tank. |
![]() |
|
| Dec 4, 2003 - Forms being laid in the cellar area beneath the kitchen in preparation for the pouring of the concrete walls. |
![]() |
|
|
November 29, 2004 - Roof-top water storage tank and wading pool concrete being poured. Also in veiw - work progressing on the facade entrance of the building. Structural architecture nearly complete on floors 1 through 3; tiles being laid in some areas and woodwork in progress. |
![]() |
|
| January 5, 2005 - Finishing plaster work completed for the front entrance facade. |
![]() |
|
| January 17, 2005 - Marble and Granite floor being layed in the lobby reception area. |
![]() |
|
| January 17, 2005 - Marble and Granite floor in lobby reception area. |
![]() |
|
|
||